The natural rate of oil-production decline at the Azeri-Chirag-Gunashli field complex has slowed from about 12% in 2023 to 3% in 2026, according to BP. The company expects to slow the decline further by year-end without increasing its operating budget.
Bakhtiyar Aslanbayli, BP’s vice president for the Caspian region, Central Asia and Turkey, presented the figures to reporters. He attributed the improvement to geosteering, multilateral and horizontal drilling, artificial intelligence and other digital technologies.
Aslanbayli said the volume of work increased while operating expenses remained roughly unchanged. The result represents a slower natural decline at a mature field rather than a return to previous peak production levels.
Karabakh Investment Decision Expected in 2027
BP also expects to make a final investment decision in 2027 on developing the Karabakh field. A construction start date has not been set because the company is still conducting calculations, choosing a development concept and assessing whether an offshore platform will be required.
The company is considering bundle technology to reduce costs. Seven-kilometer sections containing separate oil and gas pipelines as well as electrical cables would be assembled onshore, transported offshore and installed on the seabed.
Site preparation is underway near Bandovan, including work on permits, land allocation and access roads. Azerbaijan’s Energy Ministry has said Karabakh’s initially estimated geological reserves exceed 60 million metric tons of oil. BP became the project operator in 2025 with a 35% stake, while SOCAR retained 65%.
Shafag Construction on Track
Construction of the 240-megawatt Shafag solar power plant in Azerbaijan’s Jabrayil district is proceeding on schedule, BP said. Solar panels, inverters and most major equipment have been purchased and delivered to the site.
Pile installation, panel placement and the principal mechanical work have been completed in one section, where electrical installation remains. Mechanical work is continuing in another section. The company said it currently sees no serious threats to the schedule.
According to BP’s quarterly report, 50% of the solar modules had been installed by the end of September. The project employed 444 people, including about 150 residents of Azerbaijan’s recently returned territories, and peak construction employment is expected to exceed 700. Completion of the construction phase is planned for mid-2027.
Source: Vesti Baku